Catalytic projects in Durban: Point Precinct (2026 update)

The first phase of this project commenced in 2017 and has been completed, which included the provision of bulk infrastructure and the development of the Point Promenade by the City.

Overview

The Durban Point Waterfront Development is a joint venture with a Malaysian company and the Durban Point Development Company. It forms part of the City’s initiative to redevelop and regenerate the inner-city.

The revised Point Precinct Framework Plan was developed and approved in 2015. It makes provision for 750,000sqm mixed-use development including hotels, high-end residential, retail and mixed-use developments.

Point Precinct Development [Supplied: eThekwini Municipality/Invest Durban]

Progress

  • Point Promenade extension completed and opened to the public in November 2019.
  • The water main upgrade construction project of a DN800 Steel water pipe along Mahatma Gandhi Street and Anton Lembede completed.

Also see our previous update on this project

Next steps

Phase 1 of the planned developments will comprise a 35,000sqm retail mixed-use project, incorporating retail and residential components, scheduled to begin in Q1 2026 with a construction period of three to four years.

In parallel, a 35,000sqm, 30-storey hotel development is planned to commence in Q2 2026, also with an estimated three- to four-year construction period. Concept designs and market studies have been completed, and a Letter of Intent has been secured from a reputable hotel group.

The Point Waterfront Development during construction of the promenade. [Supplied: eThekwini Municipality/Invest Durban]

Challenges∗

  • Lack of development progress by Developer.
  • Legal Services is reviewing the dissolution between City & DPDC so that development can proceed unhindered.
  • The Rates Deferment Report which was circulated for signatures after the proposed amendments to the report resulted in a hold on the loan confirmation sign-off, with AFS compliance remaining outstanding.
  • Promenade transfer is in progress and is being managed by the Property Valuations and Management Directorate.
  • Dissolution of PPT & DIDT – Trustee appointment forms sent to trustees for acceptance.
  • The delay in the lease agreement with Transnet for the Durban Eye is delaying commencement of the project, which will assist in investment confidence in the city.

∗ February 2026

Project info

  • Developer: Durban Point Development Company (DPDC)
  • Investment value: R35-billion
  • City contribution: R620-million
  • Construction period: 2016 – 2030 