Project summary

  • Investment value: R10.1-billion
  • City contribution: R222-million
  • Developer contribution: R9.9-billion
  • Investor: JT Ross & Investec
  • Start and finish date: 2015 – 2035
  • Jobs created: 51 500 (Construction) and 19 000 (Operations)
  • Annual revenue: R120-million

Progress to date*

Completed Activities:
  • EIA
  • WULA
  • TIA
  • SPLUMA Applications
  • Rates Rebates MOA signed

Next steps

Old North Coast Road
  • BSC Meeting on 08/02/2021
  • BEC Meeting on 10/04/2021
  • Construction will start in July 2021 for a period of 30 months, which will finish on the 15/02/2024
Electricity
  • Finalise land purchase & registration by July 2021
Private Sector
  • Phase 1 construction to commence March 2021 for Brickworks

*At date of source publication
See historical data about the project here